(24 Nov 2023)
RESTRICTION SUMMARY:
ASSOCIATED PRESS
Uttarkashi, Uttarakhand – 24 November 2023
1. Various of tunnel exterior
2. Pan of site to tunnel entrance
3. Workers walking towards barricades, police at barricades
4. Wide of tunnel exterior, a tent pitched next to policemen standing
5. Workers sitting near tunnel entrance
6. SOUNDBITE (Hindi) Haridwar Sharma, brother of trapped worker:
“We are all hoping that they come out. Now it is not in our hands to pull them out or do anything. Administration is at it, machinery is there. With God’s blessing, we are hopeful.”
7. Mid of ambulances parked
8. Top shot of ambulances, trucks and cars parked
STORYLINE:
Rescuers racing to evacuate 41 construction workers who have been trapped in a collapsed tunnel in northern India for nearly two weeks are hoping to resume drilling on Friday after a mechanical problem a day earlier forced them to halt, officials said.
The platform of the drilling machine, which became unstable while boring through rock debris, has been fixed, Bhaskar Khulbe, a former adviser to the Prime Minister's Office, said at the accident site.
But before they can resume drilling, rescuers are manually digging through the debris to remove pieces of metal to avoid damaging the machine, said Kirti Panwar, a government spokesperson.
Drilling was also paused on Wednesday after the boring machine hit a metal girder, causing some damage to its blades and a six-hour delay as rescuers worked to clear the obstacle.
The workers have been trapped since Nov. 12, when a landslide in mountainous Uttarakhand state caused a portion of the 4.5-kilometer (2.8-mile) tunnel they were building to collapse about 200 meters (650 feet) from the entrance.
The mountainous terrain has proved a challenge for the drilling machine, which broke down earlier as rescuers attempted to dig horizontally toward the trapped workers.
The machine’s high-intensity vibrations also caused more debris to fall.
As efforts stretch into the 13th day, rescuers have drilled through 46 meters (151 feet) and need to excavate up to 12 meters (40 feet) more to create a passageway, Panwar said.
Rescue teams are inserting and welding together pipes through which the trapped workers are to escape to freedom. About 46 meters (151 feet) of pipes have been put in so far, he said.
Members of the National Disaster Response Force will then bring out the workers one by one on stretchers that have been fitted with wheels.
Officials earlier hoped to be ready to start bringing the workers out on Thursday, but now that won’t happen until Friday evening at the earliest.
Authorities have been supplying the trapped workers with hot meals made of rice and lentils through a 6-inch (15-centimeter) pipe, after days in which they survived on dry food sent through a narrower pipe. Oxygen is being supplied through a separate pipe.
Officials earlier released a video after a camera was pushed through the pipe showing the workers in their construction hats moving around the blocked tunnel while communicating with rescuers on walkie-talkies.
Most of the trapped workers are migrant laborers from across the country.
Many of their families have traveled to the accident site, where they have camped out for days to get updates on the rescue and in hopes of seeing their relatives soon.
Haridwar Sharma's brother, Sushil, is among those trapped.
“We are all hoping that they come out," he said. "With God’s blessing, we are hopeful.”
===========================================================
Find out more about AP Archive: http://www.aparchive.com/HowWeWork
Twitter: / ap_archive
Facebook: / aparchives
Instagram: / apnews
You can license this story through AP Archive: http://www.aparchive.com/metadata/you...